|
Hambantota
Port project
is
progressing
satisfactorily.
It will be
completed
even earlier
than the
scheduled
date.
According to
the Sri
Lanka Ports
Authority
nearly 76
percent of
the
breakwater
construction
work has
been
completed.
The
construction
preparation
and
cofferdam
constructions
to have been
fully
completed.
Meanwhile 90
percent of
the service
berth
constructions,
90 percent
of the
general
purpose
berth
constructions,
59 percent
of the basin
excavation,
45 percent
of the oil
berth
constructions,
42 percent
of the roads
and yards
constructions,
32 percent
of channel
dredging and
10 percent
of
administration
building
constructions
have also
been
completed.
The Chinese
pode
pre-cast is
at 100
percent
progress.
Hambantota
Port
Development
Project will
be
constructed
especially
enabling to
handle
100,000
Draft Weight
Tonnes (DWT)
vessels. It
will have an
approach
channel of
210 meters
wide and 17
meters deep.
The turning
circle at
the port
will be of a
diameter of
610 meters
at a depth
of 17
meters.
The port
will consist
of a service
vessel berth
105 meters
long, an Oil
Terminal
Berth 310
meters long
at a 17
meters depth
and a Quay
Wall (
General
Cargo) 600
meters long
at a 17
meters
depth.
The West and
East
breakwaters
constructed
for the port
are of 988
meters and
312 meters
long
respectively.
The first
stage of the
Hambantota
Port
Development
project
which is
will be
completed by
the end of
this year
ahead of
schedule.
The total
cost of the
project is
US$ 361
million.
(DN-01042010) |